Development of Rolle building

Project overview

The project will improve current facilities of Rolle building's south wing. This project will remodel the main entrance and infill the walk-through providing new accommodation. The main objectives are to improve accessibility, improve quality and deliver new and enhanced teaching spaces.

Timetable

  • The project commenced on 21 September 2017.
  • Estimated finishing date 1 June 2018.

Project milestones

  • Design and Tender - Completed.
  • Construction Commences – Achieved.
  • Construction Completion – May 2018.
  • Fit-out and Furniture – May 2018.
  • Fully operational – Monday 1 June 2018.

Disruptions

  • South wing of Rolle building (ground and first floor) will be closed during construction and fit-out.
  • Main entrance is relocated to the west side of the building.
  • South wing lift does not go lower than the second floor.
  • South wing staircase diverted between ground level and second floor.

Team

  • Project Building Surveyor - Kim Knapman.